Less than six weeks from start to finish!
Bunge Canada (Hamilton) recently awarded Bell-Camp a contract to fabricate a 150' stack to replace an existing smaller stack.
Fabricated mostly from Stainless Steel, the stack had a total weight in excess of 55 tons and was shipped to Hamilton in two pieces. A two-day, error free installation, allowed the project to be completed during Bunge’s short shut down period.
|
|
The stack was successfully fabricated and installed in less than 6 weeks thanks to Bell-Camp’s ability to keep the project on track from the kick-off meeting through to detailing and fabrication.
Once again Bell-Camp has shown its expertise in the steel fabrication business!